Oakton College is continuing campus improvement projects, including those outlined in our recently approved facilities master plan, which will result in transformed spaces that create an optimal learning and working environment for students and employees.
Check back often as this page will help minimize operational disruptions and keep you informed of our progress. You can also view areas impacted by construction on our interactive map.
The Latest Updates: March 24, 2026
Parking Lots and Roads
All roadways and parking lots will remain open and accessible to vehicle and pedestrian traffic during this period.
Office Relocations
The Division of Student Affairs has temporarily relocated to Room 2817.
|
Des Plaines and RHC (Skokie) Campus Exterior Lighting Upgrades |
|
|
Stakeholder(s): |
General campus community |
|
Percent Complete: |
|
|
Project Start: |
July 1, 2025 |
|
Project Completion: |
Summer 2026 |
|
Work has resumed onsite. |
|
|
Door and Hardware Replacement |
|
|
Percent Complete: |
10% |
|
Project Start: |
TBD |
|
Project Completion: |
TBD |
|
The Facilities department is working with the contractor to start construction on Phase 1, which entails repairs/ replacements of exterior doors at the Des Plaines and Skokie campuses. All entrances will remain open during construction. |
|
|
Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines) |
|
|
Stakeholder(s): |
Office of Student Affairs, Oakton IT, ADRC, Testing Center, Workforce Development, Bookstore, Welcome Center |
|
Percent Complete: |
5% |
|
Project Start: |
|
|
Project Completion: |
|
|
The project is expected to begin on April 6. Phase three projects for the Bookstore and Welcome Center are in design. |
|
|
Restroom Remodel Project |
|
|
Percent Complete: |
47% |
|
Project Start: |
Fall 2025 |
|
Project Completion: |
Early 2026 |
|
Work on phase one is expected to be completed in April 2026. |
|
|
TenHoeve Refresh |
|
|
Percent Complete: |
|
|
Project Start: |
|
|
Project Completion: |
Late 2027 |
|
The project is in the design phase. Architects and engineers are working on surveying the existing project areas. The design team is working on scheduling meetings with stakeholders. |
|