Construction Updates

Baseball Field Parking Lot

An image of the Oakton College Leaf on a grey b

Des Plaines Baseball Field Parking (Near College Drive Entrance)

Percent Complete

 85%

Project Start

June 2025

Project Completion

Summer 2026

This project is ongoing and includes earthwork, site preparation and concrete work. Parking surface pavers are complete. Press boxes are expected to arrive the week of July 6.

Bookstore and Welcome Center Renovations

An image of the Oakton College Leaf on a grey b

Des Plaines Bookstore, Welcome Center 

Stakeholders

Bookstore, Welcome Center 

Percent Complete

 2%

Project Start

Late Fall 2026

Project Completion

Early 2027

Phase Three projects for the Bookstore and Welcome Center have completed design and will be sent out for bidding in June. Construction will begin after completion of Phase Two.

Door and Hardware Replacement

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

13%

Project Start:

4/20/2026

Project Completion:

8/31/2026

The contractor is working to install new cable for the card reader system at both campuses. Selective work has begun at both campuses and is expected to continue throughout summer 2026.

All entrances will remain open during construction.

Exterior Lighting Upgrades

An image of the Oakton College Leaf on a grey b

Des Plaines and RHC (Skokie) Campus Exterior Lighting Upgrades

Stakeholders

General campus community 

Percent Complete:

 

Project Start:

July 1, 2024

Project Completion:

Summer 2026

Existing light poles have been removed, and removal of the light bases is underway. Landscape restoration is in progress, and lighting controls are being installed. Installation of the new emergency phones is in progress. However, the system is not yet operational.Additional updates will be provided once the new emergency phone system is activate

Office Renovations

An image of the Oakton College Leaf on a grey b

Office of Student Affairs and Workforce Development

Stakeholder(s): 

Office of Student Affairs, Workforce Development 

Percent Complete:

 50%

Project Start:

4/7/2026

Project Completion:

8/31/2026

The contractor is working on rough-in work for mechanical, electrical and plumbing systems. Drywall finishing is nearing completion. Painting is scheduled to begin the week of July 6.

Restroom Remodel Project

An image of the Oakton College Leaf on a grey b

Restroom Remodel Project

Percent Complete:

 49%

Project Start:

Fall 2025

Project Completion:

Late 2026

Phase One restrooms at the Des Plaines campus have opened.
Phase One restrooms at the Skokie campus is expected to be completed in early July.

Phase Two restroom work in rooms 2214 and 2216 at the Des Plaines campus is expected to begin in late July 2026.

Current Phase One Restroom Closures:
Skokie Campus: C103, C104, C202, C203

TenHoeve Refresh

Design phase of TenHoeve Center

TenHoeve Refresh

Percent Complete:

 0%

Project Start:

Summer 2027

Project Completion:

Late 2027

The project is in the design phase. The design team has been holding meetings with stakeholders for planning and design.