Construction Updates

Des Plaines Campus Store, Welcome Center

An image of the Oakton College Leaf on a grey b

Campus Store, Welcome Center 

Stakeholders

Campus Store, Welcome Center 

Percent Complete

 5%

Project Start

Late Fall 2026

Project Completion

Early 2027

Construction continues with an anticipated completion date in early 2027.

The Des Plaines Campus Store has temporarily relocated to room 1275 (across the hall) during construction. 

The Help Desk window has relocated to the first-floor main entrance of the Learning Commons at the Des Plaines campus.

Door and Hardware Replacement

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

30%

Project Start:

4/20/2026

Project Completion:

Late 2026


Work is scheduled to resume at a date to be determined. All doors are expected to remain accessible throughout the project.

Restroom Remodel Project

An image of the Oakton College Leaf on a grey b

Restroom Remodel Project

Percent Complete:

 50%

Project Start:

Fall 2025

Project Completion:

Late 2026

Phase one of restroom renovations are complete and all restrooms at the Des Plaines and Skokie campuses are currently open.

TenHoeve Refresh

Design phase of TenHoeve Center

TenHoeve Center Refresh

Percent Complete:

 1%

Project Start:

Summer 2027

Project Completion:

Late 2027

The project is in the design phase. The design team has been holding meetings with stakeholders for planning and design.