Construction

Appears to be an image of Oakly waving outside at Oakton College's Des Plaines campus.
  • Door 5 at the Des Plaines campus is currently closed. It is expected to re-open by Monday, Sept. 23.
  • The Division of Student Affairs has temporarily re-located to Room 2817.
  • The Division of Academic Affairs has temporarily re-located to Room 1420.
  • The Ten Hoeve Rooms at the Des Plaines campus are tentatively scheduled to be unavailable from Dec. 1, 2024 - Dec. 31, 2025.
  • Acorn and Oak Rooms at the Skokie campus are tentatively scheduled to become available Sept. 15, 2024.
An image of Oakton College's Des Plaines campus office rennovations.

Liberal Arts, Academic Affairs and Institutional Research Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Academic Affairs, Office of Liberal Arts, Office of Institutional Research

Percent Complete:

63%

Project Start:

04/08/2024

Project Completion:

01/17/2025

Phase 1 has been completed. The Liberal Arts Department has moved into Suite 2180, and the Institutional Research has moved into Suite 2100. 

Phase 2 of the construction of the Academic Affairs suites has started and will continue until the end of the year. 

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

10%

Project Start:

TBD

Project Completion:

TBD

Kluber Architects is working on construction documents for phase 1, which entails repairs and replacement to exterior doors across both campuses. Construction dates will be established upon completion of construction documents and bidding process.

An image of the master construction plan at Oakton College.

Landscape Master Plan Project

Percent Complete:

75%

Project Start:

10/23/2023

Project Completion:

10/04/2024

Work is progressing across both campuses. Entrance 5 (west entrance) at Des Plaines is expected to reopen Sept. 13

An image of the Oakton College Leaf on a grey background.

Baseball Field Renovation

Stakeholder(s):

Athletics Department

Percent Complete:

75%

Project Start:

Spring 2023

Project Completion:

Fall 2024

The infield and bullpens are 95% complete. The irrigation system is complete. Outfield finish grade is complete and sod will be installed in the coming weeks. The scoreboard will be installed in the coming weeks.

An image of the Oakton College Leaf on a grey b

Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Student Affairs, Oakton IT, ADRC, Testing Center

Percent Complete:

4%

Project Start:

 

Project Completion:

 

The progress page review meeting with stakeholders was held on Aug. 26.

Oakton Leaf logo on a gray background.

Des Plaines Library Learning Commons & Elevator Modification

Stakeholder(s):

Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk

Percent Complete:

 

Project Start:

 

Project Completion:

 

A design development review meeting with stakeholders will be scheduled during the week of Sept. 23.