Oakton College is continuing campus improvement projects including those outlined in our recently approved facilities master plan, which will result in transformed spaces that create an optimal learning and working environment for students and employees.
Check back often as this page will help minimize operational disruptions and keep you informed of our progress.
Latest Update: Sept. 16, 2024
Liberal Arts, Academic Affairs and Institutional Research Office Renovations (Des Plaines Floor 2) |
|
Stakeholder(s): |
Office of Academic Affairs, Office of Liberal Arts, Office of Institutional Research |
Percent Complete: |
63% |
Project Start: |
04/08/2024 |
Project Completion: |
01/17/2025 |
Phase 1 has been completed. The Liberal Arts Department has moved into Suite 2180, and the Institutional Research has moved into Suite 2100. Phase 2 of the construction of the Academic Affairs suites has started and will continue until the end of the year. |
Door and Hardware Replacement |
|
Percent Complete: |
10% |
Project Start: |
TBD |
Project Completion: |
TBD |
Kluber Architects is working on construction documents for phase 1, which entails repairs and replacement to exterior doors across both campuses. Construction dates will be established upon completion of construction documents and bidding process. |
Landscape Master Plan Project |
|
Percent Complete: |
75% |
Project Start: |
10/23/2023 |
Project Completion: |
10/04/2024 |
Work is progressing across both campuses. Entrance 5 (west entrance) at Des Plaines is expected to reopen Sept. 13 |
Baseball Field Renovation |
|
Stakeholder(s): |
Athletics Department |
Percent Complete: |
75% |
Project Start: |
Spring 2023 |
Project Completion: |
Fall 2024 |
The infield and bullpens are 95% complete. The irrigation system is complete. Outfield finish grade is complete and sod will be installed in the coming weeks. The scoreboard will be installed in the coming weeks. |
Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines Floor 2) |
|
Stakeholder(s): |
Office of Student Affairs, Oakton IT, ADRC, Testing Center |
Percent Complete: |
4% |
Project Start: |
|
Project Completion: |
|
The progress page review meeting with stakeholders was held on Aug. 26. |
Des Plaines Library Learning Commons & Elevator Modification |
|
Stakeholder(s): |
Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk |
Percent Complete: |
|
Project Start: |
|
Project Completion: |
|
A design development review meeting with stakeholders will be scheduled during the week of Sept. 23. |